Hi Friends,

Very good day! I want to know more about two management techniques - CPM & PERT - and what is the difference between the two. These are used to define and coordinate various activities of a project and successfully accomplish the objectives on time.

CPM analysis is activity-oriented, focusing on the start and completion of events rather than activities, whereas PERT is event or job-oriented.

Regards,
Sandeep

From India, Mumbai
Acknowledge(0)
Amend(0)

Hi, I have attached some information on CPM and PERT .I hope i will help you . Regards, PRIYA.P
From India, Madras
Attached Files (Download Requires Membership)
File Type: ppt pert_182.ppt (407.0 KB, 1590 views)

Acknowledge(1)
Amend(0)

Hi Friends,

I am Shankar Manohar, working at Wipro Technologies and pursuing my MBA in HR through Correspondence.

I have the following problem with the Pert Concept and am seeking a detailed solution. Your assistance would be greatly appreciated for my academic endeavors.

Activity Predecessor Duration(weeks)
a m b
A -- 6 7 8
B -- 1 2 9
C -- 1 4 7
D A 1 2 3
E A,B 1 2 9
F C 1 5 9
G C 2 2 8
H E,F 4 4 4
I E,F 4 4 10
J D,H 2 5 14
K I,G 2 2 8

a) Construct Project Network
b) Find Expected Duration and Variance of each activity
c) Find the critical path and expected Project Completion time
d) Probability of Completing the project by 25 weeks.

Thank you.

From India
Acknowledge(0)
Amend(0)

CiteHR is an AI-augmented HR knowledge and collaboration platform, enabling HR professionals to solve real-world challenges, validate decisions, and stay ahead through collective intelligence and machine-enhanced guidance. Join Our Platform.







Contact Us Privacy Policy Disclaimer Terms Of Service

All rights reserved @ 2025 CiteHR ®

All Copyright And Trademarks in Posts Held By Respective Owners.