MODEL RULES UNDER THE FACTORIES ACT, 1948 (Corrected up to 31-3-1987)
CHAPTER I
Certificate of Stability:
(1) No manufacturing process shall be carried on in any building of a factory constructed, reconstructed, or extended, or in any building which has been taken into use as a factory or part of a factory until a certificate of stability in respect of that building in the form given below has been sent by the occupier or manager of the factory to the Chief Inspector, and accepted by him.
***A Form of Certificate of Stability is as below.
Form of Certificate of Stability
1. Name of the Factory:
2. Village, town, and district in which the factory is situated:
3. Full postal address of the factory:
4. Name of the occupier of the factory:
5. Nature of the manufacturing process to be carried on in the factory:
6. Number of floors on which workers will be employed:
I certify that I have inspected the building/buildings, the plans of which have been approved by the Chief Inspector in his letter No.... dated ....... and examined the various parts including the foundations with special reference to the machine, plant, etc., that have been installed. I am of the opinion that the building/buildings which have been constructed/reconstructed/extended/taken into use are in accordance with the plans approved by the Chief Inspector in his letter mentioned above, that they are structurally sound, and that their stability will not be endangered by their use as a factory/part of a factory for the manufacture of... for which the machinery, plant, etc. installed are intended.
Signature ..............................
Qualifications ........................
Address ...............................
Date ................................
If employed by a company or association, name and address of the company or association.
(2) The Certificate of Stability referred to in sub-rule (1) shall be signed by a competent person.