Understanding CPM vs. PERT: How Do These Project Management Techniques Differ?

Sandeep Dhabarde
Hi Friends,

Very good day! I want to know more about two management techniques - CPM & PERT - and what is the difference between the two. These are used to define and coordinate various activities of a project and successfully accomplish the objectives on time.

CPM analysis is activity-oriented, focusing on the start and completion of events rather than activities, whereas PERT is event or job-oriented.

Regards,
Sandeep
shanpri.msw
Hi,

I have attached some information on CPM and PERT. I hope it will help you.

Regards,
PRIYA.P
1 Attachment(s) [Login To View]

shaanoh
Hi Friends,

I am Shankar Manohar, working at Wipro Technologies and pursuing my MBA in HR through Correspondence.

I have the following problem with the Pert Concept and am seeking a detailed solution. Your assistance would be greatly appreciated for my academic endeavors.

Activity Predecessor Duration(weeks)
a m b
A -- 6 7 8
B -- 1 2 9
C -- 1 4 7
D A 1 2 3
E A,B 1 2 9
F C 1 5 9
G C 2 2 8
H E,F 4 4 4
I E,F 4 4 10
J D,H 2 5 14
K I,G 2 2 8

a) Construct Project Network
b) Find Expected Duration and Variance of each activity
c) Find the critical path and expected Project Completion time
d) Probability of Completing the project by 25 weeks.

Thank you.
If you are knowledgeable about any fact, resource or experience related to this topic - please add your views. For articles and copyrighted material please only cite the original source link. Each contribution will make this page a resource useful for everyone. Join To Contribute