Dear All,
Clarifications Needed Under BOCW Act
1. The total cess amount is 1% of the project cost. Are there any specific instructions regarding the payment of this amount? For instance, should we pay this amount at the time of sanctioning, at a specific stage, or after the completion of the project?
2. Regarding registration under BOCW, should both the principal employer and the contractor register under the act, or can only the contractor register, excluding the principal employer? If both have registered, what are the implications?
3. In the registration form, under point 6, there is a sentence requesting the date of commencement and the tentative date of project completion. What should be done if the project does not finish before the tentative completion date in terms of the registration form?
Thank you in advance.
Clarifications Needed Under BOCW Act
1. The total cess amount is 1% of the project cost. Are there any specific instructions regarding the payment of this amount? For instance, should we pay this amount at the time of sanctioning, at a specific stage, or after the completion of the project?
2. Regarding registration under BOCW, should both the principal employer and the contractor register under the act, or can only the contractor register, excluding the principal employer? If both have registered, what are the implications?
3. In the registration form, under point 6, there is a sentence requesting the date of commencement and the tentative date of project completion. What should be done if the project does not finish before the tentative completion date in terms of the registration form?
Thank you in advance.