Can V Use Two 50 T Cranes To Lift A 75 T Equipment...?

itsamals@yahoo.co.in
Can v use two 50 T cranes to lift a 75 T equipment...?
boss2966
NO.
If you are planning to lift and shift within short distance in static position then if the the operators are capable of coordinating each other then it can be possible. But if you are planning to erect at some height then the capacity of the lift will get reduced based on the boom length and height.
Let us wait for the opinion / guidance from our safety expert members.
pon1965
Tandem lift is permitted provided if those cranes are of same type. e.g. one side hydraulic Crane and other side mechanically operated crane is not permitted. Before tandem lift, lifting plan and rigging study have to be conducted. The radius of the lift and SWC of Cranes shall be known before we decide the usage of Cranes. Without radius and the load chart details of the Cranes, we can't give you any suggestions.
Pon
SouravChandra
Hello!
It's my opinion that it can be harmful to use two different cranes cause it can be dangerous at any time.
Thanks & regards...
Sourav Chandra
pon1965
Sometimes, it is dangerous to lift the long or over sized materials with single Crane. Tandem lifts are universally accepted practice. In one of our project, we used 3 cranes to erect a long gallery due to ground situations. Only thing is we have to follow all safety procedures and lift plan.
Pon
boss2966
We have erected 42 Tons Raft with two 75 Ton cranes at the height of 27 meters level. In this the weight of the Girder/raft and the height it requires to be placed are to be taken into account while considering the cranes engaged for lifting and erection.
V.Raghunathan
Hello Itsamals,
My view is similar to those expressed above.
Two cranes can be used, provided it is for transfer operation at the ground level.
To use at elevated levels it has to be decided after seeing the LIFT Vs LOAD chart
of both the cranes and with the knowledge of an expert.
You should also consider the type of load. If it is uniformly distributed load, the
lifting task is relatively easy. Other wise, the uneven distribution (lop sided
objects have CG - Centre of Gravity- away from geometric centre) will pose a challenge.
Synchronization between the two operators is also a very important aspect.
V.Raghunathan
Ramesh Dharmarajan
1. Position the cranes and booms at innitial position, where the material is tobe lifted; find out the safe working load of the cranes; the re position them to where the material is to be shifted; again find out the swl; if both swls of both cranes do not exceed the actual load of the material, then lifting with tanderm or critical plan is possible
Note: In our project 7 cranes of 30ton capacity were used several times
V.Raghunathan
Hello Mr Ramesh,
You have given a good suggestion.
I need one clarification.
You have mentioned
if both swls of both cranes do not exceed the actual load of the material,
I think the combined SWL of both the cranes should be more than
the actual load to ensure Safety.
V.Raghunathan
Ramesh Dharmarajan
Hello Mr. Raghunathan
Here is the clarification
Weight of the material to be shifted - 40.0 tons
SWL of crane1 at innitial position - 30.5 tons
SWL of crane2 at innitial position - 27.0 tons
Total capacity of cranes at innitial position- 57.5 tons
SWL of crane1 at final position - 24.5 tons
SWL of crane2 at final position - 21.5 tons
Total capacity of cranes at final position-46.0 tons
In both the positions the total capacity exceed the weight of the material (40.0 tons). Here tandem/critical lift is possible.
In other words we can say that the total capacity of the cranes should be more than weight of the material at least by 10 to 15%
Ramesh Dharmarajan
If you are knowledgeable about any fact, resource or experience related to this topic - please add your views. For articles and copyrighted material please only cite the original source link. Each contribution will make this page a resource useful for everyone. Join To Contribute