BOCW Act and Factory Construction Regulations
Any construction activity with a cost of more than 10 Lakhs and not for personal use will be covered under the BOCW Act. For the construction of a compound wall within an existing factory, one must obtain approval from the Factory Inspector. The Inspector will then calculate the BOCWW Cess amount to be paid by reviewing the contract value of the construction activity. Upon payment of the BOCWW Cess, the Factory Inspector will grant approval for the construction activity.
Once approval is received, the BOCW Act no longer applies, and upon the start of construction within the existing factory premises, the Factories Act applies, similar to other factory workers. The other procedures being followed will remain unchanged. The Contract Labour Act and ISMW Act must be adhered to as usual, similar to regular construction sites.