Any construction activity with more than 10 Lakhs cost and not for own use, it will be covered under BOCW Act. For construction of Compound Wall in the existing factory, one must get the approval from the Factory Inspector. He will in turn calculate the BOCWW Cess amount to be paid by perusing the contract value of the construction activity. On payment of BOCWW Cess, the Factory inspector will sanction the approval for construction activity.
After approval the BOCW Act Ceases and on commencement of the construction activity in the existing factory premises, the factories act applies as like other factory workers.
The other procedures being followed will not have any change. The Contract Labour Act and ISMW Act will have to be followed as usual as like normal construction sites.