As per factory rules, every application for renewal shall be submitted, as nearly as possible, in Form No. 2, in duplicate, to the Chief Inspector on or before the 31st of December of the year prior to that to which the application relates. If the fees for renewal of the license are not deposited by the 31st of December, then the fees payable for renewal of the license shall be 25% in excess of the amount which would otherwise be payable if the payment of fees is made within three calendar months of the 31st of December. The fees payable for renewal shall be 50% in excess of the amount which would otherwise be payable for further default beyond three calendar months.
However, the Chief Inspector may waive the payment of excess fees if he is satisfied that there was a sufficient reason for the delay in payment.