imran_ilu49
14

Dear Senior,
I would like to know that what statutory compliance to be followed when separate building construction activity has been started by third party civil contractor having approx 200 civil labours in a factory situated in state Gujarat.??? (Statutory compliances from HR, Legal & Safety point of view)
Kindly provide me all type of registers to maintain , or any license to apply?? as i have to prepare list of such compliance to do and accordingly inform the contractor for the preparation.
Expecting your prompt inputs in this matter.
Regards
Imran

From India, Mumbai
PROFESSIONALS AND BUSINESSES PARTICIPATING IN DISCUSSION
Hemantrabi
Sr. Hr Executive
Imran_ilu49
Hr Executive
+1 Other

bhagwan-tolani
3

Dear Imran,
Greetings!!
Please note :
a. all civil labours responsibilities' of contractor not the company
b. The land owner has to take permission from land & building department to start construction or extension of the floor. Say 4th floor or 5th floor.
Rgds

From India, Delhi
imran_ilu49
14

Dear Annonymous I am talking about the Compliances, documentation work or say any license take from Company responsibilities side.???
From India, Mumbai
hemantrabi
2

Hi Imran,
Please scroll through the below mentioned point for your info:
1- Contractor must have a License under CLRA Act having having manpower strength which includes all the working labourers.
2- Notice of commencement of work need to submit to the authority.
3- If five or more inter state workers are being employed there, contractors must have license under ISMW Act.
4- If ten or more than ten building construction workers are being employed, contractor should have Registration certificate under BOCW (RE& CS Act)
5- All the amenities provided under BOCW act related to helath, safety and welfare of workers should be provided.
6- If work is being done in the premises of the factory and building which is being constructed is for a purpose of keeping finished goods of the factory in this situation BOCW act will be applicable but if Building is being constructed for the purpose of manufacturing activity then bocw act will not be applicable.
7- PF and ESIC contributions should be submitted for all workers.
8- Various registers need to be prepaired under aforesaid Acts.
9- Experts advise must be taken to full fill all the compliance.

From India, Delhi
imran_ilu49
14

Dear Hemantrabi, Thank you for you valuable suggestions.
From India, Mumbai

If You Are Knowledgeable About Any Fact, Resource or Experience Related to This Topic and Want to Be Part of Such Discussions in Future - Please Register and Log In to Cite Community.







About Us Advertise Contact Us Testimonials
Privacy Policy Disclaimer Terms Of Service

All rights reserved @ 2023 CiteHRŽ

All Material Copyright And Trademarks Posted Held By Respective Owners.
Panel Selection For Threads Are Automated - Members Notified Via CiteMailer Server