Dear Member,
I would like to add:
License Requirements for Subcontractors
It is important to check how many personnel you have taken the license for. If, as a prime contractor, you have taken the license for extra personnel (actual + projected) and the subcontractor does not require deploying 20 or more persons in Jharkhand, then your license is sufficient. However, you need to include the data of the subcontractor's employees in the Half-Yearly Labour Return.
When Subcontractors Need a Separate License
If the subcontractor is required to deploy 20 or more employees, then they can apply separately. The Form V will be issued by the Principal Employer (PE) only. They will mention, "M/s XXXXX has been engaged as a subcontractor to M/s XXXXXX (Contractor) in my establishment for XXXXXXX work."
Our Practice
In most of our sites, we generally take a license for the whole manpower (Technical, Garden, Security, Housekeeping + extra projected) and include their data in the Half-Yearly Labour Return. Our subcontractors have never taken the CLRA License.