We would like to introduce overlapping shift system (30 minutes) due to shift handing over and taking over issue. Is it require to get approval from Factories Dept.?
Please suggest.
As of now running two shifts (A & B : 6 am to 2 pm and 2 pm to 10 pm), would like to change to 6 am to 2.30 pm and 2 pm to 10.30 pm), which is more than 8 hours including lunch break.
Your query will be covered by a reading of Chapter 4 of Factories Act 1948.Sections 51 to 56 will be relevant here.