I am a contractor. I got a tender from Bhilai Steel Plant. The work requires 7 laborers per day. So, do I need to get a license from the labor department (ALC office)? As per my knowledge, a license is required for 20 or more laborers. I am asking this question because my principal employer is asking for a license copy to fill Form VII (commencement of work).
My queries are:
1. Do I need to get a license in this situation?
2. What do I need to fill in the field "license number" in Form VII (commencement of work)?
My queries are:
1. Do I need to get a license in this situation?
2. What do I need to fill in the field "license number" in Form VII (commencement of work)?