Dear HSE Professionals,
Please help me solve this problem. In our industry (Steel Pipe Manufacturing), to fulfill the requirement of the OHSAS-18001 standard, we are maintaining a Risk Assessment register.
Risk Assessment Methodology
Our risk assessment methodology is as follows: The overall OH&S hazards shall be calculated by the formula:
- Scale – A: Probability of Occurrences
- Scale – B: Severity of the Consequences
Risk = Probability of Occurrences (A) + Severity of the Consequences (B)
- Maximum Possible Value shall be = 10
- Minimum Possible Value shall be = 02
A 5 + 5 risk matrix shall be taken into consideration for the Final Risk Value.
Recently, one of the external auditors raised a Non-Conformance (NC) against this risk assessment method. He stated that this method is not acceptable and is wrong. Now, I want to prove that this method is not wrong. I need some supporting data. Please suggest.
With Regards,
Rohan Puthran.
Please help me solve this problem. In our industry (Steel Pipe Manufacturing), to fulfill the requirement of the OHSAS-18001 standard, we are maintaining a Risk Assessment register.
Risk Assessment Methodology
Our risk assessment methodology is as follows: The overall OH&S hazards shall be calculated by the formula:
- Scale – A: Probability of Occurrences
- Scale – B: Severity of the Consequences
Risk = Probability of Occurrences (A) + Severity of the Consequences (B)
- Maximum Possible Value shall be = 10
- Minimum Possible Value shall be = 02
A 5 + 5 risk matrix shall be taken into consideration for the Final Risk Value.
Recently, one of the external auditors raised a Non-Conformance (NC) against this risk assessment method. He stated that this method is not acceptable and is wrong. Now, I want to prove that this method is not wrong. I need some supporting data. Please suggest.
With Regards,
Rohan Puthran.