Factory Plan Approval and Registration Process
Regarding the question of Mr. Mohd Saud, it is first important to get the approval of the building plan/factory plan under Section 6 of the Factories Act, 1948. For that, see the Factories Rules of the respective state in which the factory falls.
For Plan Approval:
• Form No. 01 with documents like a flow chart of the manufacturing process and building plan/factory plan.
For Registration/License:
• Form No. 02 within 15 days of the occupation of the factory along with the requisite fees as per schedule.
So, Mr. Rajesh, you have to approve your factory plan first along with your construction.
Thanks,
Kumar Sanjeev