Factory Licence - Factory License [Thread 327561]

Hulukunti
Dear All,
Am workig new project, I need to take factory licence.
Please let me know wat r the documents required to submit alongwith application as it is chemical industry.
Varu123


Dear member,
Please refer the following document required.
  1. Form 1A (Certificate of Stability issued by qualified structural engineer) (in duplicate)
  2. Flow chart of the manufacturing process (in Triplicate)
  3. Land or Site Possession Certificate ( in duplicate )
  4. Certificate from Controller of Explosives (wherever explosive substances are stored or used) ( in duplicate )
  5. Treasury Receipted Chillan for having paid the prescribed fee of for Factories proposed
  6. Questionnaire Form duly filled and signed( in duplicate )
  7. Clearance certificate from the Pollution Control Board. (in duplicate )
  8. Application in Form No.1 (in duplicate).
  1. Registration application inForm No.2 duly filled with all particulars and signed by the occupier and the manager. (In Triplicate)
  2. List of directors /
  3. Partners with the memorandum of article of association / partnership deed (in Duplicate)
  4. Prescribed Fee paid challan
  1. Health and Safety policy of the proposed factory drawn and duly signed by the
    Occupier in case of factories engaged in the hazardous processes.

Regards,
Varun
9845434343