Factory License for Chemical Industry

I am working on a new project and need to obtain a factory license. Please let me know what documents are required to submit along with the application, as it is for a chemical industry.

Regards
Varu123
Dear All, I am working on a new project and I need to obtain a factory license. Please let me know what documents are required to submit along with the application as it is a chemical industry.

Dear member,

Please refer to the following documents required:

1. Form 1A (Certificate of Stability issued by a qualified structural engineer) (in duplicate)
2. Flow chart of the manufacturing process (in triplicate)
3. Land or Site Possession Certificate (in duplicate)
4. Certificate from the Controller of Explosives (wherever explosive substances are stored or used) (in duplicate)
5. Treasury Receipted Challan for having paid the prescribed fee for proposed factories
6. Questionnaire Form duly filled and signed (in duplicate)
7. Clearance certificate from the Pollution Control Board (in duplicate)
8. Application in Form No.1 (in duplicate).

Registration application in Form No.2 duly filled with all particulars and signed by the occupier and the manager (in triplicate).
- List of directors/partners with the memorandum of articles of association/partnership deed (in duplicate)
- Prescribed Fee paid challan

Health and Safety policy of the proposed factory drawn and duly signed by the occupier in case of factories engaged in hazardous processes.

Regards,
Varun
[Phone Number Removed For Privacy Reasons]
If you are knowledgeable about any fact, resource or experience related to this topic - please add your views. For articles and copyrighted material please only cite the original source link. Each contribution will make this page a resource useful for everyone. Join To Contribute