I think that you should need theses Requirements.
Contractor Required to Complete:
1. All code required life safety components.
2. Fire alarm inspected and approved.
3. Elevators inspected and approved.
4. Air balancing complete.
5. Exit lighting tested and approved.
6. Sprinkler system.
7. Fire lanes operational.
8. Emergency generator tested.
9. Painting complete.
10. All floor finishes complete.
11. All fixed equipment operational.
12. Fire caulking.
13. Telecommunications system operational.
14. Casework installed.
15. O&M Manuals given to Capital Planning and Development.
16. Final finish manual (with samples, manufacturers, catalogue numbers, color, etc. for each room) given to Capital Planning and Development.
17. Physical Plant trade training schedule submitted.
18. All training recorded on video tape.
19. Control diagrams given to Capital Planning and Development.
20. Landscape plant materials installed.
21. All plumbing fixtures clean and working.
22. All light fixtures clean and free of dust.
23. Floors polished and waxed, scrubbed, or vacuumed as appropriate for floor type.
24. Building should be cleaned and dust-free; new filters installed after cleaning.
25. Signage installed.
26. Windows cleaned interior and exterior.
27. Final punch list identified as warranty, non-complete, and needs correction, prepared with dates for completion.
28. Walk through by DSF, Capital Planning and Development, and Contractors will confirm substantial completion.
29. Substantial completion certificates issued.