To begin with, treat me as a principal employer. To do away with the resposibility under Contract Labour Act, we have awarded MAINTENANCE CONTRACT to a Contractor for carrying out certain maintenance activities for our installation for the period of 2 years. In this regard contractor has deployed 55 technician.
We only certify his monthly bills solely on the basis of jobs done in the month.
There is no mention of manpower/labour in the tender documents/contract signed between us and contractor.
Please clarify what are our responsibilities in this case with regard to ESI/Workmen Compensation/Minimum Wages Act/Contract Labour Act/PF Contribution etc.