Struggling with Manpower Scheduling in Construction? Need Urgent Help with Examples!

ryokusumo
Good day to all,

Currently, I am working in oil and gas construction as a Living Quarter Project Control. I am facing some issues with the manpower master schedule. I am seeking more examples on how to create a manpower schedule and histogram for a construction project. I require this information urgently.

Thank you very much.

Warm regards,
Ryo

[IMG]https://www.citehr.com/images/misc/progress.gif[/IMG]
ryokusumo
Hi,

Sorry if I'm not detailed. For example, when it comes to employee work hours, how can we determine the number of employees needed for a project? How do we decide when we need to hire new employees? Also, could you provide a sample of a histogram?

Before that, I believe the number of employees required is based on the project schedule planning that was made. Is that correct?

Thank you very much.