Dear All. I am presently working in a real estate firm. I require a format of work progress report for the site supervisors and site engineers engaged in site. Kindly share a proper format.
From India, Kolkata
Kritarth Consulting
195

PoSH Programs; HR Management Consultants & Trainers, Bengaluru
Just instruct the On-Site Supervisory Staff to File a "Daily Report" containing:-
1. Update on Progress- on-Target Achieved over last 24 Hrs;
2. Issueds/ Hitches faced in Target Achievement- Human Errors Or Tech /Oprns Glitches;
3. Responsible Persons Or Reasons, as the Case may be;
4. Accidents- Minor, Major or Otherwise with Acccident Investigation Report with Corrective Actions recommendaed;
5. Suggestions Submitted or Received to Improve Work Delivery, Safety of Men &
Machinery; and
6. Status of Any Inspectipn by Govet Authorities
Kritarth Team,
7 Frb 2019

From India, Delhi