Good day to all,

Currently, I am working in oil and gas construction as a Living Quarter Project Control. I am facing some issues with the manpower master schedule. I am seeking more examples on how to create a manpower schedule and histogram for a construction project. I require this information urgently.

Thank you very much.

Warm regards,
Ryo

[IMG]https://www.citehr.com/images/misc/progress.gif[/IMG]

From Indonesia, Jakarta
Acknowledge(0)
Amend(0)

Hi,

Sorry if I'm not detailed. For example, when it comes to employee work hours, how can we determine the number of employees needed for a project? How do we decide when we need to hire new employees? Also, could you provide a sample of a histogram?

Before that, I believe the number of employees required is based on the project schedule planning that was made. Is that correct?

Thank you very much.

From Indonesia, Jakarta
Acknowledge(0)
Amend(0)

CiteHR is an AI-augmented HR knowledge and collaboration platform, enabling HR professionals to solve real-world challenges, validate decisions, and stay ahead through collective intelligence and machine-enhanced guidance. Join Our Platform.







Contact Us Privacy Policy Disclaimer Terms Of Service

All rights reserved @ 2025 CiteHR ®

All Copyright And Trademarks in Posts Held By Respective Owners.