This is Ramu working in the manufacturing industry (Cement). My query is that we have received notices from the Joint Commissioner of Labor to pay building cess on the construction value. The BOCW Act is not applicable to the Factories Act as well as the Mines Act, although there was a provision in the BOCW Act. However, labor department authorities are stating that before the commencement of the manufacturing process, it is not a factory; hence, you are liable to pay building cess. The machinery value is also included in the construction value as per their notice.

Is building cess applicable to the factory? If applicable, should machinery value be included or not in the construction value?

From India, Vijayawada
Acknowledge(0)
Amend(0)

Hi Ramu,

The labor department is correct. Before the commencement of the manufacturing process, the BOCW Act is applicable. You need to pay cess on the total cost of construction activity. I think it includes machinery costs as well.

The Chattisgarh High Court recently held that the moment the manufacturing process begins in an industry, the provisions of the Factories Act would be applicable. Therefore, the provisions of the BOCW Act would cease.

You can refer to Lanco Anpara Power Ltd vs. State of Uttar Pradesh and others for the judgment delivered on October 18, 2016.

From India, Bengaluru
Acknowledge(0)
Amend(0)

Thank you very much sir for your advise
From India, Vijayawada
Acknowledge(0)
Amend(0)

Dear Praveen Bhosale ji,

Greetings and thanks for quoting the case of Chattisgarh High Court which I came to know from your post. I need to study this case law. However, what I recollect now and I have made comments somewhere on Lanco Anpara Power Ltd Vs State of Uttar Pradesh is that the SC said that unfortunately you cannot take the benefit of exclusion carved out under Section 2(1)(d) of the BOCW Act. Therefore, you have no option but to obtain a Registration Certificate under the BOCW Act and also to pay Cess even though the construction work is carried out in a factory under the FA. The SC, while coming to its conclusion, adopted a purposive interpretation of Section 2(1)(d) of the BOCW Act giving primacy to the 'superior purpose' contained in the BOCW Act and the Welfare Cess Act. This purpose is the welfare of the unorganised labour class involved in construction activity. The Hon'ble SC further held that a literal interpretation as desired by the construction companies would result in a situation where the construction workers would be deprived of the benefits of both the BOCW Act and the Factories Act, which could not have been the legislative intent. But now I am reading something different on the net regarding the SC's aforementioned judgment.

There is a need to study both the judgments once again. Experts are requested to comment on both the judgments after due study.

PS. Praveen ji, are you an ex-Siemens guy?

From India, Mumbai
Acknowledge(0)
Amend(0)

Dear Friend,

On the basis of your posting, it is difficult to provide any opinion. Please consider the following points to assess your case:

1. Is your establishment currently operating as a factory?
2. Have you undertaken any expansion at a later date?

If your establishment is not required to pay cess, then Mr. Praveen Bhosle has highlighted certain aspects for you to consider. However, if your factory is newly constructed and has commenced production, you may be obligated to pay cess.

It is recommended that you refer to the following legal references:
A) Civil Appeal No. 6223 of 2016 of the Supreme Court in the case of Lanco Anpara Power Ltd vs. UP.
B) Order of the Chhattisgarh High Court, Bilaspur Bench in WPC 2636 of 2010 dated 16/02/2018.

Furthermore, your management may pursue legal action if there are substantial grounds to challenge the demand notice.

NB: The above two cases were mentioned in a query related to gratuity eligibility.

Kindly let me know if you need any further assistance.

From India, Mumbai
Acknowledge(0)
Amend(0)

Dear sir Yes now it is a running factory. But they are demanding cess for at the time of construction value ( 2009) if we take up a expansion project, whether building cess is applicable or not Ramu
From India, Vijayawada
Acknowledge(0)
Amend(0)

On which date was the construction of the plant started and on which date did it end? Any greenfield construction falls under the B&OCW Act, and the cess levied for that period is justified.

The date on which the factory obtained a license for commercial production and the commencement of production shall be treated under the Factories Act.

As per the decision of the Chhattisgarh High Court, if you undertake an expansion project within the premises of a running factory, it would not attract the payment of cess under B&OCW.

From India, Mumbai
Acknowledge(0)
Amend(0)

Government Of Andhra Pradesh & ... vs Lakamsani Samba Siva Rao & Others on 6 August, 2015.
The Hon. Acting Chief Justice Shri.Dilip Bhosale and Hon.Justice S.V.Bhat
W.A.Nos.1012 OF 2013 and batch
Please go through the judgement. Even expansion of work within working factory has been covered under BOCW and cess needs to be paid.
While giving judgment Hon.ACJ has termed it as beneficial legislation. The construction workers are not covered under factories Act. If they won’t be covered under BOCW Act then there won’t be any benefit to them or coverage. This is most vulnerable section of society.
This was not intention of legislation. So workers need to be covered and cess needs to be paid.(Even on Machinery)
Worth reading.

From India, Mumbai
Acknowledge(0)
Amend(0)

Mr. Mohanty has given the correct opinion. Apart from Greenfield, it is applicable to running factories as written above.

Some additional information: The Act has been made effective retrospectively. Although the act was established a long time ago, rules were not framed initially. Since it has to be implemented by each state, rules were required. When the rules were published in the gazette, the state governments started levying cess retrospectively, despite their delay.

In short, even when all the work was completed 5-6 years ago, cess needs to be paid. This applies to both Greenfield projects and running factories. As BOCW implementation is recent, there are very few cases to refer to. Unless the Supreme Court creates a sufficient database of cases, the situation will continue with some cases in favor of owners and some against.

From India, Mumbai
Acknowledge(0)
Amend(0)

Join Our Community and get connected with the right people who can help. Our AI-powered platform provides real-time fact-checking, peer-reviewed insights, and a vast historical knowledge base to support your search.







Contact Us Privacy Policy Disclaimer Terms Of Service

All rights reserved @ 2025 CiteHR ®

All Copyright And Trademarks in Posts Held By Respective Owners.