Dear sir, Contractor is quoting 1 paisa as service charge in financial bid and after getting contract, he starts exploitation of contract labour by recovering Rs 50 to 100/- day. Moreover, he threatens those labours who are not giving desired money back to the contractor. In addition to this, Contractor fulfills all statutory compliance while submitting the monthly bills i.e. EPF/ESI/Wages sheet statement shows that minimum wages has been paid to the labour.
Can we take any action against the contractor in above scenario ?

From India, undefined
Dear Mr. Tiwari,
This a classic case of exploitation of contract labor by the contractor. If there is no other issue (Political, rules etc.), please remove the contractor immediately. Set some proper norms as follows:-
1. Find out actual cost of the contractor - Minimum wage + Employer's portion of PF & ESI + some reasonable service charge + GST as applicable.
2. Reimburse the above and when Bonus, Gratuity, Leave pay etc. payable - please also reimburse the same in actual.
3. Every month cross check from contract labor if there is any exploitation or not.
As a PE it is your responsibility to protect the contract labor - forget about legally but socially.
Thanks & Regards,
S K Bandyopadhyay ( Howrah, WB)
USD HR Solutions
+91 98310 81531

From India, New Delhi
This discussion thread is closed. If you want to continue this discussion or have a follow up question, please post it on the network.
Add the url of this thread if you want to cite this discussion.






About Us Advertise Contact Us
Privacy Policy Disclaimer Terms Of Service



All rights reserved @ 2020 Cite.Co™