Thread Started by #Dp Shukla

Do anybody know the procedure of Chief Inspector approval for working of worker upto 12 hour in any day as mention in Section 56 of the Factories Act 1948?
16th January 2018 From India, undefined
Section 56 does not permit working upto 12 hours, it is only allowing spread over of 12 hours. Factories Act lays down that the daily hours of work shall not exceed 9 hours (Section 54), however Section 65 empowers the Chief Inspector of factories to exempt by written order the total number of hours of work on any day as not exceeding 12 hours on the ground that the exemption is required to enable the factory to deal with exceptional pressure of work. The other conditions for the exemption is given in the Section 65 which may be perused. This provision was utilised on innumerable occasions by moving a self explanatory application explaining the requirement for exemption and pursuing the matter with the Chief Inspector. There have been no occasion where the request was not agreed.
16th January 2018 From India, Mumbai
Thank you sir for clarification.
17th January 2018 From India, undefined
Reply (Add What You Know) Start New Discussion

Cite.Co - is a repository of information created by your industry peers and experienced seniors. Register Here and help by adding your inputs to this topic/query page.
Prime Sponsor: TALENTEDGE - Certification Courses for career growth from top institutes like IIM / XLRI direct to device (online digital learning)





About Us Advertise Contact Us
Privacy Policy Disclaimer Terms Of Service



All rights reserved @ 2019 Cite.Co™