Dear sir, Kindly tell me in my company there are 50 employees and their working hours is 8. but sometimes some of them do work more which is not more than one hour each .. so some of them work 9 hour which counts as their overtime suppose 35 workers worked 8 hours in a day and remaining 15 workers worked 9 hours in a day than how can we calculate mandays?
From United Arab Emirates, Abu Dhabi
PROFESSIONALS AND BUSINESSES PARTICIPATING IN DISCUSSION
Skhr07
Hr Advisor
KK!HR
Management Consultancy
Abbasiti
Assistant Engineer, Indian Telephone Industries,
Saqibhse
Hse Officer

abbasiti
517

Dear Saqibhse, If 35 worked for 8 hrs, it is 35 man days. If 15 worked for 9 hrs, it is 15x9/8 = 16.875 man days. (Total 35+16.875 = 51.875 man days). Abbas.P.S
From India, Bangalore
sasikumar-p
Man days calculation for annual days. In case worked in 35 staffs means how many man days
From India, Bengaluru
KK!HR
1400

Eight hours of work is considered as a man day, so by calculating the total number of hours and dividing it by eight, the man-days can be calculated
From India, Mumbai
skhr07
6

you will have to calculate mandays like below

Arrive at the no of days worked by the company: total days in the month-weekend-national holidays
No.of worked days by the company*No of total employees-no of leave taken

Eg: 31 days in Jan'22-10 weekly off-1 national holiday= 20 working days

Mandays=20*1200-700=23300

From India, Chennai

If you are knowledgeable about any fact, resource or experience related to this topic - please add your views.







About Us Advertise Contact Us Testimonials
Privacy Policy Disclaimer Terms Of Service

All rights reserved @ 2023 CiteHRŽ

All Material Copyright And Trademarks Posted Held By Respective Owners.
Panel Selection For Threads Are Automated - Members Notified Via CiteMailer Server