| Hi Friends,
Iam Shankar Manohar working in Wipro Technologies and doing my MBA in HR thru Correspondance. I have a following problem in Pert Concept and looking for a solution on this. Please give me a solution in detail for this problem if possible. It will be of a great help for me in my academics. Activity Predecessor Duration(weeks) a m b A -- 6 7 8 B -- 1 2 9 C -- 1 4 7 D A 1 2 3 E A,B 1 2 9 F C 1 5 9 G C 2 2 8 H E,F 4 4 4 I E,F 4 4 10 J D,H 2 5 14 K I,G 2 2 8 a) Construct Project Network b) find Expected Duration and Variance of each activity c) Find critical path and expected Project Completion time d)Probabilty of Completing the project on 4 b4 25 weeks. |