Dear All, Am workig new project, I need to take factory licence. Please let me know wat r the documents required to submit alongwith application as it is chemical industry.
From India, Pune
Varu123
3



Dear member,
Please refer the following document required.
  1. Form 1A (Certificate of Stability issued by qualified structural engineer) (in duplicate)
  2. Flow chart of the manufacturing process (in Triplicate)
  3. Land or Site Possession Certificate ( in duplicate )
  4. Certificate from Controller of Explosives (wherever explosive substances are stored or used) ( in duplicate )
  5. Treasury Receipted Chillan for having paid the prescribed fee of for Factories proposed
  6. Questionnaire Form duly filled and signed( in duplicate )
  7. Clearance certificate from the Pollution Control Board. (in duplicate )
  8. Application in Form No.1 (in duplicate).
  1. Registration application inForm No.2 duly filled with all particulars and signed by the occupier and the manager. (In Triplicate)
  2. List of directors /
  3. Partners with the memorandum of article of association / partnership deed (in Duplicate)
  4. Prescribed Fee paid challan
  1. Health and Safety policy of the proposed factory drawn and duly signed by the
    Occupier in case of factories engaged in the hazardous processes.

Regards,
Varun
9845434343

From India, Bangalore
Community Support and Knowledge-base on business, career and organisational prospects and issues - Register and Log In to CiteHR and post your query, download formats and be part of a fostered community of professionals.





Contact Us Privacy Policy Disclaimer Terms Of Service

All rights reserved @ 2024 CiteHR ®

All Copyright And Trademarks in Posts Held By Respective Owners.