No Tags Found!

oberoi.tanuj
Hi,
Im working as a Site Engineer i need to prepare a daily report like how many labours, masons, Electricans and plumbers etc have worked on site and what they have worked how much have been completed and what going to do for tommorow. Can anybody help me out in this i will be very thankful.can you provide me format for this
more at https://www.citehr.com/300218-daily-...#ixzz174OMaqYi

From India, Chandigarh
sunilcms
1

You can chalk our twom format
1. Daily Attendance mention the name of the employee along with Designation
2. Being engineer you must know the Project Mangement
You may have got the various activities to be completed with start and end date for each subactivities
You can list out all the activities to be done to comlete the project and mention the start date and end date against each activity. Put this in excel sheet. also puet 1 -30 nos on the top to write each day work completed
end of the day can write in front of activities adding separate column ( 1- 30 colum as per attendance in separete column
when ever required you can refer the work done sheet to see what the progress of work and attendanace sheet to check who were present to complete the work done on particular day.
I have tried to suggest you this format . You may use if faund useful
Thanks
Sunil Nipurte

From India, Pune
Attached Files (Download Requires Membership)
File Type: xls formatforProject.xls (23.0 KB, 357 views)

Community Support and Knowledge-base on business, career and organisational prospects and issues - Register and Log In to CiteHR and post your query, download formats and be part of a fostered community of professionals.





Contact Us Privacy Policy Disclaimer Terms Of Service

All rights reserved @ 2024 CiteHR ®

All Copyright And Trademarks in Posts Held By Respective Owners.